Work on the Andover Bus Station continues with completion still planned for mid-June 2014, just two months away.
This is the April update from Test Valley Borough Council.
Update from TVBC
The bus station is taking on good form.
Internally the café the floor has been laid, electrical and mechanical systems have been installed and the roof works are completed. The internal and external cladding to the café will soon start.
The office space for Test Valley Community Services and Stagecoach is well progressed and decoration and installation of fixtures and fitting will start after Easter.
The cladding works to the main concourse roof is complete with the exception of the two curved ends, which is about to progress.
The kerbing for the bus apron has commenced which give shape to the forecourt are and the external works to the highway will start after Easter the period holidays.
The works to the waterproof the multi-storey car park will finish at Easter. Completion of the works are still planned for mid-June, with an official opening in July 2014.

Would have been fantastic if you the money could have been found to clad the car park exterior as well – would have made this relatively large building look far more modern.